Concrete Pour Planner
Plan a slab, beam or footing pour: cement bags, sand, crush, water, mixer batches, pour time, crew and curing / cube test dates.
Loading the calculator… (JavaScript is needed)
About this tool
Enter the size of the slab or members and the mix. You get the materials to stock, mixer batches and hours, a crew size and the dates for curing and cube tests.
How it's calculated
- Dry volume = 1.54 × wet volume, split by the mix ratio
- One batch per bag of cement in a one-bag mixer
- Curing 7 days (OPC) or 10 days (blended cement)
How many bags of cement for a 5 inch slab of 1,000 sq ft?
About 417 cft of concrete; in 1:2:4 that is roughly 75 bags of cement (about 6.3 bags per m³).
How long should a slab be cured?
At least 7 days for OPC and 10 days for slag or fly-ash cement, keeping it continuously wet.
Results are calculated from the values you enter using standard formulas. Download the PDF to keep a record. Contractors, architects and designers can print reports with their own logo with Kataria Pro. For certified design or construction, talk to our engineers.
Kataria Engineering & Consultancy Services (2026). Concrete Pour Planner [online calculator]. https://katariaengineering.com/tools/concrete-pour-planner.html