Formwork (Shuttering) Area & Striking Time
Shuttering area for slabs, beams and columns, sheets and props needed, and the earliest dates to remove formwork per IS 456.
Loading the calculator… (JavaScript is needed)
About this tool
Enter slab, beam and column sizes and the casting date to get the contact area, plywood sheets, props and a striking schedule.
How it's calculated
- Contact area of soffits, sides and column faces
- Sheets of 8 × 4 ft with 10% for cuts; props at about 3 ft centres
- Striking periods from IS 456 clause 11.3
When can slab shuttering be removed?
Soffit formwork after 3 days with props left under; props for spans up to 4.5 m after 7 days, longer spans after 14 days (OPC, normal weather).
Results are calculated from the values you enter using standard formulas. Download the PDF to keep a record. Contractors, architects and designers can print reports with their own logo with Kataria Pro. For certified design or construction, talk to our engineers.
Kataria Engineering & Consultancy Services (2026). Formwork (Shuttering) Area & Striking Time [online calculator]. https://katariaengineering.com/tools/formwork-shuttering-calculator.html